Julian Brown runs a South Florida landscaping company, and his wife, Carol, keeps the books. Together they maintain about 60 yards a month. When a homeowner hired them to rip out grass and lay artificial turf around a playground on his property, they finished the turf in less than 10 days. Then they spent weeks waiting for the last $13,000.

The money only started moving after the couple went to the Help Me Howard team at WSVN 7News, which reported the story on Nov. 18.

A $20,000 backyard job

According to 7News, the customer works in the entertainment industry. He wanted the grass removed and artificial turf installed around a playground and other areas of the property, a project that totaled more than $20,000.

He paid a $7,000 deposit. The Browns completed the turf in under 10 days and sent a request for the $13,000 balance. The customer then asked for changes, and Julian made them.

When Carol followed up about the balance, the station reported, the customer said he didn’t know when they would be paid. The couple had used about $4,000 from their own bank account to finish the property. After that, communication stopped.

What happened after 7News called

Once the station got involved, a publicist for the client responded. The publicist said the client had only needed the company to finish the work before paying the balance, and that now that the job was completed, the client’s “accounting department will be taking care of the balance.”

Julian told the station he couldn’t believe it and thanked the team for stepping in.

Howard’s advice to the Browns was persistence. The scope and the price had been agreed and the work was done, so the couple was entitled to be paid, he said. He also mentioned a lien as an option, while warning that it comes with fees and can take a long time. For future jobs, he recommended getting everything in writing, including the amount and the due date, and asking for a larger deposit.

How a lien works for a landscaper in Florida

Florida’s construction lien law covers people who improve a property, not just builders. Under section 713.05 of the Florida Statutes, a contractor or laborer in a direct contract with the owner has a lien on the improved property for money owed under that contract, but the lien arises only once a claim of lien is recorded.

There is a clock. Section 713.08 says the claim must be recorded no later than 90 days after the final furnishing of labor, services or materials, and it has to list the unpaid amount, the dates of first and last work, the owner’s name and a legal description of the property.

Even then, the lien doesn’t last forever. Under section 713.22, it expires one year after it is recorded unless a lawsuit to enforce it is filed within that year. That is the cost and delay Howard was describing.

The paperwork is lighter for someone like the Browns, who dealt with the homeowner directly. The detailed notice-to-owner steps in section 713.06 apply to subcontractors and suppliers who are not in a direct contract with the owner.

The fine print small businesses learn the hard way

The Browns’ case shows how fast a small yard business can end up financing a client. They covered roughly $4,000 out of pocket to finish, on top of the labor they had already put in, while the larger share of the bill sat unpaid.

Howard’s checklist was simple: write down the price and the due date, get a bigger deposit up front, and keep following up. In this case, the follow-up that worked was a phone call from a TV station.